A case involving acquisition of an easement is called a partial taking. The property rights retained by the owner are called the remainder. Michigan’s jury instruction relating to partial takings summarizes some of the key issues raised in partial taking cases:
This case involves what is known as a “partial taking”; that is to say, the property being acquired by the condemning authority is part of a larger parcel under the control of the owner.
When only part of a larger parcel is taken, as is the case here, the owner is entitled to recover not only for the property taken, but also for any loss in the value to his or her remaining property.
The measure of compensation is the difference between (1) the market value of the entire parcel before the taking and (2) the market value of what is left of the parcel after the taking.
In valuing the property that is left after the taking, you should take into account various factors, which may include: (1) its reduced size, (2) its altered shape, (3) reduced access, (4) any change in utility or desirability of what is left after the taking, (5) the effect of the applicable zoning ordinances on the remaining property, and (6) the use which the condemning authority intends to make of the property it is acquiring and the effect of that use upon the owner’s remaining property.
Further, in valuing what is left after the taking, you must assume that the condemning authority will use its newly acquired property rights to the full extent allowed by the law.
The bold language is critical to understanding the just compensation issues arising from a partial taking. If a utility acquires rights in an easement, it must pay for those rights even if they lack a present intention to fully implement them.
Homes may suffer negative aesthetics; impacts from tree removal like loss of privacy, shade, and buffering from noise or wind; and limitations on the ability to add or expand structures. Wind issues are often pronounced in agricultural areas. Removal of trees close to a home may require additional air conditioning or irrigation for yards. Utility lines can generate unpleasant humming or buzzing noises.
Many easements prohibit any new construction in a swath of property on either side of their poles or pipelines. Some property may enjoy a highest and best use for future development that must be included, even if the owner does not intend to do so. Utility easements that limit construction of buildings or planting of trees limits development. Easements can reduce density and increase site costs for development parcels. I have handled numerous matters where civil engineers have prepared before and after site plans demonstrating that less could be developed and that the impact is greater on a percentage basis than the amount of land subjected to the easement. Further, building around the easement was more costly on a per unit basis. Some projects impact property that is in close proximity to highly developed areas, where the values likely include acknowledgment of the potential for future development.
Farm fields face different types of impacts. Poles or even pipeline easements that include the right to install above ground facilities, like drips, valves, regulators, fittings, meters and other equipment and appurtenances as may be necessary or convenient for its operations. This can impact farming.
Pipeline construction can involve open trenching. Transmission lines require deep excavation to construct the foundation of for the poles. This can result in soil mixing and all types of construction can involve compaction, which impacts farming. Most utility easements do not incorporate requirements to minimize construction impacts by doing things like avoiding mixing topsoil with other excavated soil types.
Just compensation is owed for temporary construction areas, which can also suffer compaction and soil mixing.
The easement must be evaluated in terms of how access is gained. Some easements restrict access to just the utility corridor, some identify access points outside the corridor, and some allow the utility to travel wherever they please.
The loss of woodlands can reduce value. The easement’s general restoration provision does not address how things like cut trees and stumps will be addressed.
Michigan allows recovery of future costs incurred to avoid business interruption. This would include projected expenses to restore yields in impacted fields by taking steps like planting cover crops or engaging in extra tilling.
These are just a few of the issues that commonly arise for utility takings.